20% ROI — Efficiency You Can Measure, Returns You Can Trust
↑↑↑
Production
20%
Fuel Saved
0
Steam Traps
Challenges & Solution
Original situation
Baseline data showed 136 kg of fuel per ton of product from Nov ’24 – Jun ’25.
Steam traps and control valves caused condensate buildup, uneven heat transfer, and energy losses.
Objectives:
Reduce fuel cost per ton
Ensure consistent quality and drying
Implement solution with no downtime
Technical modification
i-Kcal engineered & commissioned Jetomat TurboHeat as a turnkey retrofit for the corrugator line.
Eliminated traps and steam losses
Boosted internal steam velocity and heat transfer
Delivered uniform surface temperature in dryers and hot plates
Installed with no downtime, ensuring uninterrupted production
The implementation of Baelz retrofit with Jetomat TurboHeat® in place of traditional control valves has resulted in approximately 20% fuel savings, elimination of steam traps, complete automation of heating & better drying quality.
The Jetomat® Turboheat® technology has proven to be an effective solution for enhancing energy efficiency and process performance.
Benefits of Jetomat Turboheat
-
-
-
-
-
Item description
Case Study Overview
Located in Morbi, Gujarat, a major corrugation hub, the plant produces high-volume corrugated sheets for packaging. Rising fuel costs and pressure on margins pushed the management to look for a solution that could cut energy use without disrupting production.
Result / Numbers / Matrices
Period
Fuel (kg/ton)
Baseline (Nov ’24 – Jun ’25)
136
July ’25
113
August ’25
108
16.8%
~22
~36
CO₂ Avoided (tons)
Saving % vs Baseline
–
Fuel Saved (tons)
–
–
Conclusion
This project demonstrates that proven technology + expert engineering = measurable ROI.
Jetomat TurboHeat, delivered by i-Kcal Systems, enabled the plant to cut fuel use from 136 to 108 kg/ton while maintaining consistent output and quality.
For corrugators, this is not just an efficiency upgrade — it’s a step toward sustainable, cost-competitive growth.
20.6%
~23
~38
Budget (Indicative)
The project was executed as a turnkey retrofit within a planned maintenance budget. The payback period is expected to be less than 18 months based on the 18–20% monthly savings.
Project Details
Location: Morbi, Gujarat
Technology: Steam system retrofit with Jetomat TurboHeat®
Industry: Corrugated Packaging
Company: Corrugator Plant (Confidential name with held)